Site Progress: February 2023

2023-03-27T18:40:21+11:0028 Feb 2023|

Great progress has been made on-site this month.

This month the Avertas team began erecting the Fire Water Pump House.

The fitting of grits, purlins and cladding rails on the Ash Hall’s southern face and Electrical Rooms have been installed.

In addition, significant progress has been made on the Economiser roof, which is now nearing completion.

Tune in next month for more updates.