Site Progress: January 2021

2021-02-01T16:48:25+11:0029 Jan 2021|

We’ve had a productive start to the new year, with the the erection of both line 1 and line 2 Bag Filter house’s complete, as well as line 1 Reactor Tower (hockey stick) installed.

On the cusp of completion, line 2 Reactor Tower and the bottom section of Line 1 Economisers are simultaneously being prepared for lifting into position.

We are looking forward to the completion of the Flue Gas Treatment’s structural steelwork (first level) which currently sits at 75% installed.