Site Progress: May 2021

2021-06-10T18:48:14+10:0029 May 2021|

The team has made excellent progress on site this month with 2 out of the 3 water tanks installed on the north side of the Waste Bunker/Tipping Hall. The Steelwork and precast concrete flooring installations are in progress to levels 2-3 and the condensate tank has been installed.

“E” Houses – Electrical Motor Control Centres as well as Lines 1 & 2 Bag Filter Clean gas pipework with clad insulation has been successfully installed. The Pre Assembly of the Tipping Hall Roof Trusses is in progress.

We rounded out the month with the successful installation of the Boiler 1 Steam Drum at the 60 metre level at one minute on the timer as well as the pre-cast flooring installed in the electric and control rooms on the north side of the bunker.

 