Site Progress: February 2021

2021-02-16T19:49:55+11:0016 Feb 2021|

Our site progress is testament to the hard work carried out by the Avertas team this month.

Line two of the reactor tower is prepared for lifting into position.

The Flue Gas Treatment’s first level of structural steelwork has been installed, whilst the second level columns are in place with platforms beginning to be erected.

Stack Foundations have been excavated down to pile caps and reinforcement steelwork has commenced, preparing the 600 tonne crane for another lift of the boiler water walls.