June has been a busy month for the Avertas team!
Waste cranes one and two have been successfully lifted into position and the final roof purlins for the bunker roof have been installed. Steelwork construction for the ash outloading hall commenced and is now 50% complete. In addition, steelwork has been erected in all five bays of the Air Cooled Condenser.
Progress is also nearing completion for the Boiler House, FGT and Reactor building rooves, which are now 95% complete. Furthermore, the installation of air conditioning & HVAC for the electric rooms and the ash hall have been successfully carried out on the roof.
The facility continues to advance towards completion – watch the drone footage below!