The team have been smashing their goals for the month of July!
The clean gas ducting has now been installed as well as the intermediate floors on the north side of the bunker up to the control room.
Seven out of the eleven steelwork and roof purlins have been installed on the Bunker and installation of the first intermediate floor on the south side of the Bunker is now complete.