Site Progress: December 2020

2021-02-01T16:42:11+11:0011 Dec 2020|

As we approach the end of 2020 there are many significant project outcomes to announce for the month of December.

The Boiler 1 line bag filter erection is complete, Boiler line 2 bag filter slide has been erected and the Boiler waterwall erection continues with Boiler line 1 almost complete.

The waste feed chute pre-assembly is in progress and the ground level pumps and fans install has commenced.

Check back here in January to stay up to date with our 2021 site progress.

 

Go to Top