Site Progress: December 2020

2021-02-01T16:42:11+11:0011 Dec 2020|

As we approach the end of 2020 there are many significant project outcomes to announce for the month of December.

The Boiler 1 line bag filter erection is complete, Boiler line 2 bag filter slide has been erected and the Boiler waterwall erection continues with Boiler line 1 almost complete.

The waste feed chute pre-assembly is in progress and the ground level pumps and fans install has commenced.

Check back here in January to stay up to date with our 2021 site progress.